DOE EM Update – West Valley Grouts Underground Cell in Advance of Major Demolition

November 3, 2020 – EM and cleanup contractor CH2M HILL BWXT West Valley (CHBWV) recently began grouting a large underground cell at the West Valley Demonstration Project (WVDP) to provide structural stability for when heavy demolition equipment operates aboveground to tear down the Main Plant Process Building.

The cell, which is nearly 30 feet below ground, will remain in place until the underground portion of the Main Plant Process Building is removed in the future. Crews continue to prepare the building for demolition. Link to update