EM Update – Crews Safely Remove West Valley Main Plant Ventilation Stack

September 18, 2018 – Workers recently removed an estimated 20,000-pound ventilation stack from the Main Plant Process Building at EM’s West Valley Demonstration Project (WVDP) Site.

“Once again, the CHBWV team did an excellent job in their pre-planning and execution of this challenging work,” WVDP Director Bryan Bower said referring to cleanup contractor CH2M HILL BWXT West Valley. “This work evolution will forever change the landscape of the WVDP site, and will become a reminder of the ongoing progress here.” Link to article