DOE EM Update – West Valley Safely Demolishes Sixth Ancillary Facility Surrounding Main Plant

August 18, 2020 – Crews recently demolished the 6,955 square foot Utility Room building (UR) at the West Valley Demonstration Project. Built in 1964, the UR was used to produce and distribute various utilities required for Main Plant processes. This is the sixth of seven Main Plant support structures demolished, and brings EM’s total number of structures removed at West Valley to 67.

The UR was constructed with a steel frame, concrete block, and masonry exterior. The single story building measures 79 feet wide, 88 feet long and 23 feet high. Link to Update